Public Notice: Main Street Rehabilitation Project 2022
UPDATE: November 1, 2022 – Partial Temporary Closure of Legion St., Liverpool
Effective the morning of Tuesday, November 1, 2022, Legion Street, Liverpool, NS will be reduced to one lane, and will be, in effect, temporarily a one-way street. Traffic flow will be from Main St. to Henry Hensey Dr., and traffic will not be able to access Legion Street from Henry Hensey Dr. travelling to Main St. Signage will be in place noting detours.
This temporary partial street closure is in effect to enable work to progress on the Main Street Infrastructure Renewal Project. We apologize for any inconvenience that is caused while this necessary work takes place.
****
UPDATE: October 5, 2022 – Temporary Water Disruption Overnight in Liverpool
As part of the Main Street Infrastructure Renewal project currently taking place in Liverpool, NS, there will be a temporary water disruption for those properties near the intersection of Main Street and Summer Street while crews work to install a water valve in the intersection. Water will be turned off at approximately 3:00 am tomorrow morning and is expected to be restored by early morning when the work is completed. Work is being completed in the late night hours to minimize disruption to users of the system as water in the area will be turned off.
Properties in the work area, as well as surrounding areas, may experience discoloured water once the repair has been completed and are asked to flush their cold water tap until the water clears.
We apologize for any inconvenience caused while this necessary work takes place.
****
UPDATE: September 15, 2022- Temporary Street Closure and Water Disruption Continues on September 15, 2022
The water valve work that is taking place as part of the Main Street Infrastructure Upgrade project in Liverpool will be continuing today. Temporary street closures and water disruptions will continue today, Thursday, September 15, 2022, as outlined below:
Street Closure– Main St. between Legion St. and Old Bridge St. will be closed to through traffic to facilitate water valve work. Detours will be in place.
Water Disruption– Main St. between Summer St. and Jubilee St. as well as surrounding areas may experience a disruption in water service throughout the day to facilitate valve work as part of the Main St. Infrastructure Upgrade.
We thank you for your patience as we complete this necessary work.
***********************************************************************************
UPDATE: September 13, 2022 – Temporary Street Closure and Water Disruption
Please note the following temporary street closure and water disruption in effect in Liverpool on Wednesday, September 14, 2022.
Street Closure- Main St. between Legion St. and Old Bridge St. will be closed to through traffic to facilitate water valve work. Detours will be in place.
Water Disruption- Main St. between Summer St. and Jubilee St. as well as surrounding areas may experience a disruption in water service throughout the day to facilitate valve work as part of the Main St. Infrastructure Upgrade.
We thank you for your patience as we complete this necessary work.
********************************************************************
UPDATE: September 2, 2022 Main Street Closure
Main Street will be closed to through traffic beginning Tuesday, September 6, 2022 as crews start the Main Street phase of the project. During this phase traffic and pedestrian access will be limited on Main Street between McLeod and Legion Streets. Main Street will remain closed for the remainder of the project.
Traffic control and detours will be in place throughout the project.
We appreciate your patience as we complete this important work.
**********************************************************************************
UPDATE: September 2, 2022 Municipal Water Disruption
Water Utility Customers along Main Street between the McLeod and Legion Streets as well as Weir Lane and surrounding areas will experience water disruption Tuesday, September 6, 2022 as crews install temporary water lines. The installation of temporary lines will maintain service as the new water main is installed.
We appreciate your patience as we complete this important work.
**********************************************************************************************
UPDATE: August 9, 2022, 3:46 p.m.
Henry Hensey Dr will be closed to through traffic as sanitary and storm water connections are made. Henry Hensey Dr will reopen once work is complete.
Traffic control and detours will be in place throughout the project.
We appreciate your patience as we complete this important work.
**********************************************************************************************
August 9, 2022; Liverpool, NS: BEGINNING AUGUST 9TH, 2022 construction will commence in the areas of Main St between McLeod and Legion St as the Region of Queens begins the Main Street Rehabilitation Project.
The scope of the project will include the replacement of century old water and sewer lines as well as the installation of a new storm sewer and complete road rebuild along Main St. Additionally, the sewer main that connects Main St. to the existing pumping station on Henry Hensey Dr. will be upgraded. The project will start August 9th and continue to late autumn.
Residents and the general public can expect dust, noise as well as road and sidewalk disruptions. Traffic control and detours will be in place throughout the project.
Questions regarding the project can be directed to Garrett Chetwynd, E.I.T., Assistant Director of Engineering & Public Works (gchetwynd@regionofqueens.com or 920-354-7157).